Eight people, one client, about thirty-four weeks. Follow a turnkey fit-out from the first conversation to the day the keys change hands. See who does what, on which day, in which screen, and how it all ends up in one project file.

9Stages
8Stakeholders
238Days, Turnkey
0 W4 W8 W12 W16 W20 W24 W28 W34
07 Billing runs alongside · Day 105 → 238
Drawn to scale: one tick a day, a long tick a weekPhase lengths are the Turnkey template's defaults · your plan will differ
  1. 01 BriefDay 0
  2. 02 RecceDay 0–3
  3. 03 DesignDay 3–61
  4. 04 BOQ & QuoteDay 61–75
  5. 05 ProcurementDay 75–105
  6. 06 ExecutionDay 105–217
  7. 07 BillingDay 105–238
  8. 08 SnagsDay 217–231
  9. 09 HandoverDay 231–238
Day 0Before the brief
The cast

Eight people. One project file.

Pick someone to follow. Their part of the job lights up across the programme below and in every stage further down the page.

Following everyone. Choose a person above, or use the Follow menu in the bar.
Who 01 BriefDay 0 02 RecceDay 0–3 03 DesignDay 3–61 04 BOQ & QuoteDay 61–75 05 ProcurementDay 75–105 06 ExecutionDay 105–217 07 BillingDay 105–238 08 SnagsDay 217–231 09 HandoverDay 231–238
ClientGets the brief as a linkSigns off the recceReceives meeting minutesApproves the quote by link—Reads the weekly reportPays milestone invoicesWalks the snag listReceives the handover file
Project DirectorNew project on the dashboard—Tracks milestonesSigns off pricing—Portfolio dashboardBilled vs collectedSnag closure rateProject closed
DesignerWrites the client briefJoins and signs the recceDrawings and revisionsBuilds the BOQ—Revises drawings for site——As-built drawings
Project ManagerCreates project from templateReviews and signs the recceReviews design tasksSends the quotationApproves indentsWeekly report to clientApproves measurement booksCloses snagsHandover checklist
Site Engineer—Measures every room——Raises material indentsDaily DPR, offlineRecords measurementsLogs snags with photosFinal walkthrough
Procurement————RFQ and comparisonTracks deliveries———
Accounts———Milestone payment planPurchase orders—GST invoices, RA bills—Retention and final bills
Subcontractor—————Works on sitePaid against RA billsFixes snags—
Done in the appHappens in person, recorded by someone else in the app
01Day 0 · Site notebook

It starts with a conversation.

The designer turns the client's wish list into a structured brief from a template. The PM creates the project from Turnkey, Consultancy or Design & Build, and the plan is ready before anyone visits site.

In the appClient BriefBrief templatesNew project from templateShare link
Client Brief · CB-0007Finalised · shared
Project type
Healthcare · clinic fit-out
Carpet area
4,800 sq ft, ground floor
Spaces
Reception (12 seats), 4 consult rooms, lab, pantry
Look and feel
Calm, easy to clean, brand colours supplied
Must keep
Existing AC ducting, main entrance
Target opening
About 8 months
Template: Healthcare brief · 6 sectionsExample

Who does what

CLClient

Shares needs in a meeting, then receives the finalised brief as a link to check.

Link
DSDesigner

Fills the brief from a template, section by section, and finalises it.

Client Brief
PMProject Manager

Creates the project from a template. Tasks, phases, milestones and dependencies come with it, assigned by project role.

Projects
PDProject Director

Sees the new project appear on the executive dashboard.

Dashboard
02Day 0–3 · Site notebook

Measure it once. Sign it off once.

The site engineer records every room, the site's condition and its services on a phone, even in a basement with no signal. Designer, PM and client each sign the recce. A change makes a new revision you can compare line by line.

In the appSite RecceMeasurementsClient sign-off linkRevision compare
Recce · Ground floorRev 2
RoomL ftW ftH ftArea sq ft
Reception241810432
Consult 1121010120
Consult 2121010120
Corridor30510150
Total so far822
Power 25 kW · water point · no liftExample
DesignerApproved · Day 2OK
Project ManagerApproved · Day 2OK
ClientAccepted from link · Day 3Dr. A. ClientAccepted

Who does what

SESite Engineer

Measures each room, notes site condition, power, water and access, and adds photos. Works offline and syncs later.

Site Recce
DSDesigner

Joins the recce and signs off as a stakeholder.

Site Recce
PMProject Manager

Reviews, follows up on open recce actions, and signs.

Recce actions
CLClient

Accepts the recce from a link on their phone with a typed name. The PM can also record a sign-off given in person.

Sign-off link
03Day 3–61 · Drawing sheet

Concept to working drawings

Concept, design development and working drawings run as tasks on a board and a Gantt. Every drawing lives in a register with its revision history, so nobody builds from Rev B when Rev C exists.

In the appKanbanGanttDrawing registerMinutes of meetingTimers
RECEPTION CONSULT 1 CONSULT 2 LAB PANTRY CORRIDOR 80'-0" △C
DrawingA-102 · Reflected ceiling plan
ProjectClinic fit-out · GF
StatusFor construction
Revisions
RevIssueDay
AConcept10
BDesign dev.31
CWorking58
Example

Who does what

DSDesigner

Works through design tasks, uploads drawings and issues each new revision with a status. One-tap timers log the hours.

Drawing register
PMProject Manager

Moves tasks through review on the board and watches phase health on the Gantt.

Kanban · Gantt
CLClient

Attends design meetings. Receives the minutes as a link with decisions and owners.

MOM link
PDProject Director

Sees milestones and team load across all projects.

Dashboard
04Day 61–75 · Drawing sheet

Priced, approved, awarded

The BOQ is built from the drawings. The quotation carries a milestone payment plan, and the client approves it from a link. Once it's awarded, the plan the template created is the programme everyone works to.

In the appBOQQuotationMilestone paymentsApproval link
BOQ · Section 4 · Ceilings Example
ItemQtyUnitRate ₹Amount ₹
4.1 Grid ceiling, consult240sq ft8520,400
4.2 Gypsum ceiling1,240sq ft951,17,800
4.3 Cove light pelmet180rft14025,200
Section total1,63,400
QTN-0012 · Rev 2Valid 15 days
₹ 18,50,000 + GST
20%Advance
30%Mobilisation
30%Fit-out
20%Handover
Ask for changesApprove
Programme · Turnkey templateDay 0 → 238
Design
BOQ & quote
Procurement
Civil & MEP
Fit-out
Snags · handover

Who does what

DSDesigner

Builds the BOQ section by section from the drawings and the recce measurements.

BOQ
PMProject Manager

Turns the BOQ into a quotation with revision number and validity, and sends the approval link.

Quotation
ACAccounts

Sets the milestone payment plan that later becomes the client's invoices.

Milestones
CLClient

Approves or asks for changes from a link. The time is recorded on the quotation.

Approval link
PDProject Director

Signs off pricing and margin before the quote goes out.

In person
05Day 75–105 · On site

Buy what the site actually needs

Indents come from site with quantities and a need-by date. Approved indents become RFQs to several suppliers, with a comparative statement showing who's cheapest. Orders and receipts are standard ERPNext purchasing.

In the appMaterial indentRFQ from indentComparative statementERPNext purchasing
Indent · MI-0031140 boards

Gypsum board 12.5 mm, needed on site by Day 110. Raised by the site engineer.

RFQ · 3 suppliersApproved

The PM approves the indent. Procurement sends it to three suppliers in one step.

Comparison · per board
Supplier A₹ 412
Supplier B · lowest₹ 398
Supplier C₹ 405
Example

Who does what

SESite Engineer

Raises indents from site with items, quantities and the date they're needed.

Material indent
PMProject Manager

Approves the indent. Approval always needs a live connection, so it's never replayed from stale data.

Approve indent
PRProcurement

Creates the RFQ from the indent and compares quotes side by side.

RFQ · comparison
ACAccounts

Raises purchase orders and books supplier invoices in ERPNext.

ERPNext
06Day 105–217 · On site

Every day on site, on record

Mobilisation, civil and MEP, then fit-out: sixteen weeks of site work. The site engineer files a DPR every evening, offline if needed. On Friday the week's DPRs roll up into a weekly report the client reads from a link.

In the appDPRWeekly report (WPR)Site visitsMOMOffline sync
18:05No signal
Daily Progress ReportClinic fit-out · Day 154
Saved on this phone · 3 changes to sync
Clear · work not hampered
Carpentry6Electrical3False ceiling4
62%
Submit needs a connection
Day 154Week 22 of 34 · fit-out
MonDPRSent
TueDPRSent
WedDPRSent
ThuDPRSent
FriWPRShared
SatDPRQueued
WPR 22

The week's progress, photos and hold-ups, sent to the client by email or WhatsApp as a link and a branded PDF.

Who does what

SESite Engineer

Files the DPR with manpower, equipment, progress and hold-ups. Saves offline, submits once there's signal.

DPR
PMProject Manager

Reviews DPRs and submits and shares the weekly report. Logs site visits and meetings.

WPR · Site visit
CLClient

Opens the weekly report link, with earlier weeks one tap away.

WPR link
DSDesigner

Answers site questions with a revised drawing. Everyone sees the new revision.

Drawing register
PRProcurement

Follows deliveries against orders and receipts.

ERPNext
SCSubcontractor

Does the work. Their output is measured on site for billing.

On site
PDProject Director

Sees the latest DPRs and projects at risk across the portfolio.

Dashboard
07Day 105–238 · The ledger

Two ledgers, kept straight.

Billing runs alongside the site work, in both directions. The client is invoiced by milestone, with GST and retention. Subcontractors are paid by measurement: the measurement book becomes an RA bill with TDS, retention and advances worked out. Both post to ERPNext accounts.

In the appMilestone invoicesMeasurement bookRA billProject finance
Money in · clientMilestone 2 · Mobilisation
QuotationMilestoneSales invoice
30% of ₹ 18,50,0005,55,000
GST @ 18%99,900
Invoice total₹ 6,54,900

Retention per invoice is tracked until release. Example

Money out · subcontractorRA Bill 03 · False ceiling
Measurement bookApprovedRA bill
This bill 420 of 1,240 sq ft @ ₹ 4016,800
Less TDS @ 1%−168
Less retention @ 5%−840
Net payable₹ 15,792

Previous bills: 820 sq ft. Rates as configured. Example

Who does what

SESite Engineer

Records what each subcontractor completed in the measurement book.

Measurement book
PMProject Manager

Approves the measurement book, online only, and reopens it if a quantity is wrong.

Approve MB
ACAccounts

Raises milestone invoices with GST and creates RA bills from approved measurement books.

Invoices · RA bill
SCSubcontractor

Gets paid against each RA bill, with deductions shown line by line.

Receives payment
CLClient

Pays each milestone invoice.

Pays
PDProject Director

Sees billed, collected and outstanding by month, and the top outstanding projects.

Dashboard
08Day 217–231 · Site notebook

Find it, photograph it, close it.

Two weeks to clear everything the walkthrough finds. Each snag gets a captioned photo, a location, a severity and an owner. Closure is tracked until the list reaches zero.

In the appSnag listCaptioned photosSeveritySnag closure rate
SN-014 · ReceptionHairline crack at ceiling joint
photo · before
MediumOpen
SN-015 · Consult 2Paint patch behind door
photo · after
LowDay 224
SN-016 · LabDoor closer not latching
photo · before
HighAssigned
Snag closure Example82% · 41 of 50 closed

Who does what

SESite Engineer

Logs each snag with photos and captions, and submits it. Works offline on site.

Snag list
SCSubcontractor

Fixes the snags assigned to their trade.

On site
PMProject Manager

Checks the fix and closes the snag.

Snag list
CLClient

Walks the site with the team and adds anything they spot.

Walkthrough
PDProject Director

Watches the snag closure rate: green from 80%, amber from 50%.

Dashboard
09Day 231–238 · The project file

Hand over the file you worked in.

No week of assembling a dossier at the end. The brief, the signed recce, every drawing revision, every DPR, every bill and the closed snag list are already in one project. The handover checklist confirms it's all there.

In the appHandover checklistProject filesShared documentsRetention
01 · Client briefCB-0007
03 · DrawingA-102 Rev C
06 · SiteDPR · Day 154
07 · LedgerRA Bill 03
09 · Handover checklistClinic fit-out · ground floor
  • As-built drawings · 14 sheets, latest revisions
  • Snag list · 50 of 50 closed
  • Warranties and O&M manuals · 9 files
  • Keys and access cards · handed over
  • Retention release · due after the defects period
Example

Who does what

PMProject Manager

Works through the handover checklist and attaches the final documents.

Handover checklist
DSDesigner

Issues as-built drawings as the final revision in the register.

Drawing register
CLClient

Receives the handover documents as links instead of a box of paper.

Shared documents
ACAccounts

Raises the final milestone invoice and tracks retention until it's released.

Project finance
SESite Engineer

Does the final walkthrough with the client.

On site
PDProject Director

Marks the project completed. It leaves the active list with its full history.

Dashboard
Day 238

Bring one live project. We'll map its journey.

In a 45-minute demo we set up your project from a template and walk it from brief to handover with your own team's roles. Write to info@innosync.in.